Home›Concrete Footing Calculator
Concrete Footing Calculator
Work out exactly how much concrete a footing needs — strip footings under walls, rectangular pad footings, or round pier footings — in cubic yards and bags, with waste and a cost estimate.
Calculate your footing concrete
A strip footing is a long trench under a wall; a pad footing is a single square or rectangular block under a post or column; a round pier is a cylinder, usually poured in a Sonotube. All three are volume = area × depth, divided by 27 for cubic yards. One 80 lb bag yields 0.60 ft³, one 60 lb bag 0.45 ft³ (Quikrete / Sakrete data sheets).
Your results
How the concrete footing formula works
Every footing is a volume problem: measure the shape, multiply its dimensions, and convert cubic feet to cubic yards (27 ft³ per yd³). The shape changes the area; the rest is the same.
Strip or pad footing: volume (ft³) = length (ft) × width (ft) × depth (ft) × count
Round pier footing: volume (ft³) = π × (diameter ÷ 2)² × depth (ft) × count
Cubic yards: yd³ = ft³ ÷ 27
80 lb bags: bags = ft³ ÷ 0.60, rounded up (60 lb bag = 0.45 ft³, 40 lb = 0.30 ft³)
With waste: order = volume × (1 + waste %)
Depth is usually given in inches, so divide by 12 first: a 12 in deep footing is 1 ft deep, an 8 in footing is 0.667 ft. Width is the trench width, not the wall width — a footing is wider than the wall it carries (typically 16 in wide for an 8 in wall). This matches the Inch Calculator footing method: rectangular pad L × W × D ÷ 27, circular pad π × r² × D ÷ 27, strip footing linear feet × width × depth ÷ 27.
Worked example
A strip footing 40 ft long, 16 in wide, 12 in deep under a garden wall:
Volume: 40 × 1.333 × 1 = 53.33 ft³
Cubic yards: 53.33 ÷ 27 = 1.98 yd³
With 10% waste: 53.33 × 1.10 = 58.67 ft³ = 2.17 yd³
80 lb bags: 58.67 ÷ 0.60 = 97.8 → 98 bags
Ready-mix cost: 2.17 × $150 = $326
Four pad footings, each 24 × 24 in and 12 in deep: one pad is 2 × 2 × 1 = 4 ft³, four pads are 16 ft³ = 0.59 yd³; with 10% waste that is 17.6 ft³, or 30 bags of 80 lb mix. A round pier 12 in in diameter and 4 ft deep is π × 0.5² × 4 = 3.14 ft³ — about 6 bags of 80 lb mix.
How much does footing concrete cost? (US, 2026)
Prices are 2026 US planning ranges. Ready-mix is priced per cubic yard by the supplier; bagged mix is priced per bag at the retailer. Check local prices before ordering.
| Item | Typical price |
|---|---|
| Ready-mix concrete, delivered | $125–$200 per yd³ (typical $150) |
| 80 lb bag of concrete mix | $6–$9 |
| 60 lb bag of concrete mix | $5–$7 |
| 40 lb bag of concrete mix | $4–$5 |
| Short-load fee (orders under 1 yd³) | $75–$150 |
| #4 rebar, 20 ft stick | $8–$12 |
| Form lumber, 2×12 × 8 ft | $12–$18 |
Waste allowance
Add 10% for an uneven trench and spillage — the standard figure for footings, because a dug trench is never as neat as the drawing. Use 5% only on a clean, machine-dug trench with exact dimensions, and 15% on rough ground or where the trench walls keep caving in. Footings are buried, so a little extra concrete is cheap insurance; a short pour is a cold joint.
Frequently asked questions
How much concrete do I need for a footing?
Multiply length × width × depth (all in feet) and divide by 27 for cubic yards. A 40 ft strip footing, 16 in wide and 12 in deep, is 40 × 1.333 × 1 = 53.33 ft³ = 1.98 yd³ — order 2.17 yd³ with 10% waste, or 98 bags of 80 lb mix.
How many bags of concrete for a footing?
Divide the volume in cubic feet by 0.60 for 80 lb bags (0.45 for 60 lb, 0.30 for 40 lb) and round up. Four 24 × 24 × 12 in pad footings are 16 ft³ — 30 bags of 80 lb mix with 10% waste.
How deep should footings be?
Below the local frost line — that is the rule in the IRC (R403.1.4). In warm climates 12 in below grade is often enough; in cold climates the frost line can be 36–48 in deep. The footing must also be at least 12 in wide for an 8 in wall, and it should sit on undisturbed soil, never on fill.
What is the difference between a strip footing and a pad footing?
A strip (continuous) footing is a long trench that runs under a whole wall. A pad (isolated) footing is a single square or rectangular block under one post or column. A round pier is a cylinder, usually poured in a Sonotube form. The math is the same — area × depth — only the shape changes.
Can I pour footings with bags instead of ready-mix?
Yes, up to about 1 yd³. A yard of concrete is 45 bags of 80 lb mix (about $315 at $7 a bag), while a ready-mix yard is about $150 — but the truck adds a short-load fee of $75–$150 on small orders, so bags win on small jobs and ready-mix wins above roughly 1–2 yd³.