Home›Concrete Cost Calculator
Concrete Cost Calculator
Price a concrete pour from its size — ready-mix by the yard, delivery and short-load fees, reinforcement and finishing labour — and see the total and the cost per square foot.
Calculate your concrete cost
Ready-mix is sold by the cubic yard; a truck holds about 10 yd³ and most suppliers charge a short-load fee under 1 yd³ (sometimes under 2 yd³). The finishing labour line is labour only — a fully installed slab, forms and all, typically runs $6–$12 per sq ft all-in.
Your results
How concrete cost is calculated
A concrete price has four parts. The concrete itself is the biggest line on a big pour; on a small pour the delivery fee and the labour can be bigger than the concrete.
Volume: yd³ = length (ft) × width (ft) × thickness (ft) ÷ 27 × (1 + waste %)
Ready-mix: material = yd³ × price per yd³
Delivery: short-load fee, usually $75–$150 under 1 yd³
Reinforcement: rebar or mesh, by the stick or by the sq ft
Finishing labour: labour = area (sq ft) × $ per sq ft
Total: material + delivery + reinforcement + labour
The break-even between bagged mix and ready-mix is about 1 yd³: one yard is 45 bags of 80 lb mix (about $315 at $7 a bag) against about $150 for a ready-mix yard — but the truck adds a short-load fee on small orders, so bags win below roughly 1 yd³ and the truck wins above it. This matches the SiteCalc cost model: ready-mix $/yd³, short-load fees, delivery, reinforcement, forms and finishing labour as separate lines.
Worked example
A patio slab 12 × 12 ft, 4 in thick, at $150/yd³ ready-mix:
Volume: 12 × 12 × 0.333 = 48 ft³ = 1.78 yd³
With 10% waste: 48 × 1.10 ÷ 27 = 1.96 yd³
Ready-mix: 1.96 × $150 = $293
Reinforcement: $60 (mesh + a few rebar sticks)
Finishing labour: 144 sq ft × $3 = $432
Total: 293 + 0 + 60 + 432 = $785 — $5.45 per sq ft
A 20 × 20 ft driveway, 6 in thick, is 200 ft³ = 7.41 yd³ (8.15 with waste); at $150/yd³ the concrete alone is $1,222, and the all-in price with labour is typically $4,500–$7,000. A small 4 × 4 ft pad, 4 in thick, is 0.20 yd³ — under the 1 yd³ minimum, so expect a $75–$150 short-load fee on top of the $30 of concrete, or buy 10 bags of 80 lb mix for about $70 instead.
How much does concrete cost? (US, 2026)
Prices are 2026 US planning ranges from supplier and retailer lists. Ready-mix prices vary by region and mix strength (3,000 vs 4,000 psi). Check local prices before ordering.
| Item | Typical price |
|---|---|
| Ready-mix concrete, delivered | $125–$200 per yd³ (typical $150) |
| Short-load fee (under 1 yd³) | $75–$150 |
| Delivery beyond the free radius | $0–$100 |
| 80 lb bag of concrete mix | $6–$9 (45 bags = 1 yd³) |
| #4 rebar, 20 ft stick | $8–$12 |
| Welded wire mesh, 6×6 | $0.30–$0.50 per sq ft |
| Finishing labour | $2–$4 per sq ft |
| Full installed slab (all-in) | $6–$12 per sq ft |
| Stamped / decorative concrete | $12–$18 per sq ft |
Waste allowance
Add 10% for an uneven subgrade and spillage — the standard figure for a slab pour. Use 5% only on a level, well-compacted subgrade with exact forms, and 15% on rough ground or where the subgrade was over-dug. Waste is money here: 10% on a 10 yd³ pour is a whole extra yard.
Frequently asked questions
How much does concrete cost per cubic yard?
Ready-mix concrete typically costs $125–$200 per cubic yard delivered in 2026, with $150 a good planning figure. Small orders under 1 yd³ add a short-load fee of $75–$150, and delivery beyond the free radius can add $0–$100.
How much does a 12x12 concrete slab cost?
A 12 × 12 ft slab, 4 in thick, is 1.78 yd³ (1.96 with 10% waste). The ready-mix is about $293 at $150/yd³; with $60 of reinforcement and $432 of finishing labour the total is about $785 — $5.45 per sq ft. A fully installed slab by a contractor typically runs $6–$12 per sq ft all-in.
What is a short load fee?
A fee suppliers charge when you order less than a full truckload — usually under 1 yd³, sometimes under 2 yd³. It is typically $75–$150 and covers the truck coming out for a small pour. On a 0.2 yd³ pad the fee can cost more than the concrete, which is why small jobs are usually done with bags.
Is it cheaper to buy concrete in bags or ready-mix?
Ready-mix is cheaper per yard: one cubic yard is 45 bags of 80 lb mix (about $315 at $7 a bag) against about $150 for a ready-mix yard. But the truck adds a short-load fee on small orders, so bags win below roughly 1 yd³ and ready-mix wins above it — and bags also win when the site has no truck access.
How much does concrete cost per square foot?
Materials only: about $2–$3 per sq ft for a 4 in slab ($150/yd³ ÷ 27 × 0.333 ft). With reinforcement and finishing labour, $5–$6 per sq ft. Fully installed by a contractor, $6–$12 per sq ft for plain concrete and $12–$18 for stamped or decorative.